Picture1

Picture2

Test process:

  1. Top heating 100% power
    Bottom heating 0% power
    Duration: 2 minutes
  1. Top heating 0% power
    Bottom heating 100% power
    Duration: 2 minutes
  • If during the test the operational conditions were correct:
    • Top and Bottom lamps will light up one after the other
    • Top and Bottom sensors and PCB sensor will show the same result
  • In case one of the sensors cools instead of heats then it was connected with replaced polarity.
  • If the Top and/or Bottom sensors’ graphs are inconsistent, it may be a sensor fault. First check if the PCB sensor has not lost its connection to the PCB as that may affect the process.

Duration of these tests are 2-2 minutes.

 

Back to eC-reflow mate overview